Question 72: CIA II Practice Exam

Question 72:

  1. An internal auditor is preparing to conduct an assurance engagement with the organization’s bidding and contracting function. The engagement plan has not yet been completed, but the internal auditor schedules a meeting with the management of the function to help develop a good working relationship and to request the function’s help in preparing for the audit. The internal auditor prepares an agenda of items to review with management. Has the internal auditor proceeded correctly in this scenario?

 

 

 

 

 

 

 

 